Lighthouse project: A proposed timeline

advertisement | advertise on newsday

Lighthouse developers say construction

would take eight to 10 years.

Phase I (4-5 years)

Installation of infrastructure: electricity, water, sewage systems

Coliseum (21/2 years)

Canal zone: Construction of canal lined with shops, residences, and convention and exhibition center

Residences: Half of the 2,306 units (lofts above stores, tower units, condos)

Two 36-story towers

Celebration Plaza, a landscaped park between canal and towers.

advertisement | advertise on newsday

Phase II(4-5 years)

Construction of movie theater

Balance of residential units

Construction of office space and sports

technology center