Lighthouse developers say construction

would take eight to 10 years.

Phase I (4-5 years)

Installation of infrastructure: electricity, water, sewage systems

Coliseum (21/2 years)

Canal zone: Construction of canal lined with shops, residences, and convention and exhibition center

Residences: Half of the 2,306 units (lofts above stores, tower units, condos)

Two 36-story towers

Celebration Plaza, a landscaped park between canal and towers.

Phase II(4-5 years)

Construction of movie theater

Balance of residential units

Construction of office space and sports

technology center

Previewing Hochul's State of the State ... Proposed Jamaica station redesign ... LI Works: Pinball repair Credit: Newsday

Details on accused Gilgo killer's first day in custody ... Fresh Grocer closing ... Proposed Jamaica station redesign ... Expanded cancer treatments

Previewing Hochul's State of the State ... Proposed Jamaica station redesign ... LI Works: Pinball repair Credit: Newsday

Details on accused Gilgo killer's first day in custody ... Fresh Grocer closing ... Proposed Jamaica station redesign ... Expanded cancer treatments

SUBSCRIBE

Unlimited Digital AccessOnly 25¢for 6 months

ACT NOWSALE ENDS SOON | CANCEL ANYTIME