Lighthouse project: A proposed timeline
Lighthouse developers say construction
would take eight to 10 years.
Phase I (4-5 years)
Installation of infrastructure: electricity, water, sewage systems
Coliseum (21/2 years)
Canal zone: Construction of canal lined with shops, residences, and convention and exhibition center
Residences: Half of the 2,306 units (lofts above stores, tower units, condos)
Two 36-story towers
Celebration Plaza, a landscaped park between canal and towers.
Phase II(4-5 years)
Construction of movie theater
Balance of residential units
Construction of office space and sports
technology center