LIPA will spend $109 million for two large energy-storage batteries to help with soaring summer energy demand in the Hamptons, officials said Wednesday, as part of a portfolio of projects that includes a $1.62 billion wind farm and a $513 million grid upgrade for the South Fork.

PSEG Long Island on Wednesday also confirmed it had installed 30 megawatts of emergency generators to help with peak summer demand on the South Fork and Shelter Island. The temporary, oil-fueled generators provide backup power for the regions and are rarely used. Costs weren’t disclosed, but in the past PSEG has said the 12 megawatts of generators for Shelter Island cost $650,000 for the summer. East Hampton will get 12 megawatts of back-up generators, and Montauk will get 6 megawatts.

LIPA trustees on Wednesday approved authorizing LIPA to finalize a 20-year contract for two 5-megawatt storage batteries, which will store energy for use primarily during the high summer peak season on the South Fork, where electric use is growing at around 2.5 percent a year, even as the rest of Long Island sees a reduction. They will be in place in 2018.

LIPA officials during the board meeting also detailed a previously reported long-term plan for future energy sources for Long Island, called an Integrated Resource Plan. The long-delayed plan found that while LIPA on the whole won’t need new power sources until at least 2035, the authority will contract for some 800 megawatts of renewable resources, such as offshore wind and solar, to displace aging fossil-fuel-based plants that LIPA has recommended not be upgraded or replaced.

Public hearings on the plan will take place June 21-22 in Suffolk and Nassau.

LIPA officials, pressed at the board meeting for the costs of expanding the renewable energy sources, reiterated previous statements that variables were too wide-ranging and speculative to disclose now. LIPA did have a specific figure — $5 billion — for the costs of overhauling two older power plants and building a new one.

“We frankly did not do a thorough evaluation of [the] complex renewable costs,” LIPA chief executive Tom Falcone said, because it’s a “highly uncertain and rapidly changing industry.”

To navigate those changes, LIPA is taking a “modular” approach to contracting for renewables, Falcone said, and bringing those projects before the board for approval as they were needed to meet state commitments. He called it “the best way to approach the process because you really have no idea what else is going to go on in the world. What is the relative cost of solar versus offshore wind? What’s the cost of hydro[power]? What are other utilities going to do?”

But trustee Matthew Cordaro said it was important for ratepayers to know the costs before LIPA commits. The Leisure Village Association of all-electric senior residences in Ridge has previously questioned LIPA’s decision to foot the bill for primarily summertime Hamptons peak power sources.

Noting he was “not speaking out against clean energy,” Cordaro said, “We should know, our ratepayers should know, what our investment is in the clean energy plan and how it factors into some of the decisions in this” resource review.

Supporters for LIPA’s renewable-centric plan crowded the board meeting, including union members who urged LIPA to approve a second, 210-megawatt wind farm. Environmentalists praised LIPA and the trustees for moving away from a future powered by fossil fuels. Gordian Raacke of Renewable Energy Long Island called the plan “historic,” and said, “I encourage you to continue to invest in offshore wind.”

Bruce Miller, a trustee of the Village of Port Jefferson, which is locked in a tax challenge with LIPA, accused the utility of failing to make good on past plans to overhaul the power plant there. He questioned the South Fork wind farm plan. “What a huge burden on ratepayers to serve only Hamptons part-time residents.”

Construction work zone safety … UBS Arena MTV Music Awards … Girls softball league Credit: Newsday

Gilgo-related search in Suffolk woods ... Urologist trial update ... Construction work zone safety ... Jericho fatal crash

Construction work zone safety … UBS Arena MTV Music Awards … Girls softball league Credit: Newsday

Gilgo-related search in Suffolk woods ... Urologist trial update ... Construction work zone safety ... Jericho fatal crash

Latest Videos

Newsday LogoSUBSCRIBEUnlimited Digital AccessOnly 25¢for 5 months
ACT NOWSALE ENDS SOON | CANCEL ANYTIME